Contractors for the City of Fredericksburg completed removal of the boardwalk, except for the piers, on Sunday, May, 1. The fencing for passage through the Anderson Center site is fully installed and the bridge is now again open for crossing Route 1. The City plans to resume work for the removal of the piers on Wednesday, 5/4/11 with completion anticipated on Thursday, 5/5/11. (Photo from UMW FaceBook by Eric Grube Sr)
Pedestrian Bridge Reopened
May 3, 2011 by